Q. The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
  • (A) Slowly rise
  • (B) Slowly drop
  • (C) Drop sharply and then level out
  • (D) Rise sharply and then level out
πŸ’¬ Discuss
βœ… Correct Answer: (A) Slowly rise