Q. The strategy used to correct resource over-allocations by balancing demand for resources and the available supply is known as
  • (A) resource assignment
  • (B) resource leveling
  • (C) resource splitting
  • (D) resource scheduling
πŸ’¬ Discuss
βœ… Correct Answer: (B) resource leveling