Q. It is necessary to carry out a feasibility study as
  • (A) top management can not ensure that a project is feasible before calling a system analyst
  • (B) top management is not sure what they want from the system
  • (C) even though top management is in favor of the system, technology may not be mature for implementation
  • (D) all organizations do it
πŸ’¬ Discuss
βœ… Correct Answer: (C) even though top management is in favor of the system, technology may not be mature for implementation