Q. What do we call a formal comparison of the actual costs and benefits of a project with original estimates?
  • (A) Post-completion audit
  • (B) Feedback audit
  • (C) Cost-benefit analysis
  • (D) Business scorecard report
πŸ’¬ Discuss
βœ… Correct Answer: (A) Post-completion audit