Q. The assumption in PERT is
  • (A) A project is always behind schedule
  • (B) Cost of project is always more than the estimated cost
  • (C) A project can be sub-divided into a set of predictable, independent activities
  • (D) Activities are complex in nature and time taken by them are indeterminate
πŸ’¬ Discuss
βœ… Correct Answer: (C) A project can be sub-divided into a set of predictable, independent activities