πŸ“Š Cost Accounting
Q. Loss which unavoidable on account of inherent nature of production processes is
  • (A) Abnormal loss
  • (B) Normal loss
  • (C) Process loss
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (B) Normal loss
πŸ“Š Cost Accounting
Q. The sum of value of work certified and uncertified appearing in the contract account is called
  • (A) Work in process
  • (B) Work completed
  • (C) Work in progress
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) Work in process
πŸ“Š Cost Accounting
Q. Work which has been done but not certified is called
  • (A) Work uncertified
  • (B) Work certified
  • (C) Extra work
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) Work uncertified
πŸ“Š Cost Accounting
Q. The determination of EBQ is influenced by the following factors:
  • (A) Rate of consumption
  • (B) Manufacturing cost
  • (C) Storage cost
  • (D) All of the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All of the above
πŸ“Š Cost Accounting
Q. Batch costing is a form of specific order/job costing where the cost per unit is ascertained by _________ the total cost of a batch by the number of items produced in that batch.
  • (A) dividing
  • (B) multiplying
  • (C) subtracting
  • (D) adding
πŸ’¬ Discuss
βœ… Correct Answer: (D) adding
πŸ“Š Cost Accounting
Q. Job Costing is suitable for
  • (A) Ship-builders
  • (B) Furniture makers
  • (C) Printing presses
  • (D) All of the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All of the above
πŸ“Š Cost Accounting
Q. The first step in a job order cost procedure is
  • (A) Receiving of order
  • (B) Estimation of the price of the job
  • (C) Production order
  • (D) Receiving an enquiry
πŸ’¬ Discuss
βœ… Correct Answer: (D) Receiving an enquiry
πŸ“Š Cost Accounting
Q. Each job has a ______ prepare for it that bears the job number and which is used to collect all cost data relating to job.
  • (A) Job time sheet
  • (B) Job Cost Card
  • (C) Job ticket
  • (D) Job Account
πŸ’¬ Discuss
βœ… Correct Answer: (B) Job Cost Card
πŸ“Š Cost Accounting
Q. Contract costing is specialized system of job costing applies to _____ contracts.
  • (A) Short-term
  • (B) Medium-term
  • (C) Long-term
  • (D) Continuous process
πŸ’¬ Discuss
βœ… Correct Answer: (C) Long-term
πŸ“Š Cost Accounting
Q. The sum of value of work certified and uncertified appearing in the Contract Account is called
  • (A) Work in Progress
  • (B) Work in Process
  • (C) Work completed
  • (D) Work done
πŸ’¬ Discuss
βœ… Correct Answer: (A) Work in Progress