M Mr. Dubey • 100.64K Points Coach Math Bookmark Embed Report View In MB-Short Q. A and B together can do a work in 8 days, B and C together in 6 days while C and A together in 10 days, if they all work together, the work will be completed in : (A) 4 4/9 days (B) 5 5/47 days (C) 3 3/4 days (D) 3 3/7 days Correct Answer - Option(B) Views: 742 Filed under category Math Share