Q. A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
  • (A) 5
  • (B) 5.5
  • (C) 6
  • (D) 8
βœ… Correct Answer: (C) 6