U Uday Singh • 7.23K Points Tutor III Math Bookmark Embed Report View In MB-Short Q. A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in : (A) 4 days (B) 6 days (C) 8 days (D) 18 days Correct Answer - Option(A) Views: 575 Filed under category Math Share