Q. A and B can do a piece of work in 18 days, B and C in 24 days, A and C in 36 days. In what time can they do it all working together ?
  • (A) 12 days
  • (B) 13 days
  • (C) 16 days
  • (D) 26 days
βœ… Correct Answer: (C) 16 days