Q. In two days A, B and C together can finish 1/2 of a work and in another 2 days B and C together can finish 3/10 part of the work. Then A alone can complete the whole work in ?
  • (A) 15 days
  • (B) 10 days
  • (C) 12 days
  • (D) 14 days
βœ… Correct Answer: (B) 10 days