Q. Working efficiencies of P and Q for completing a piece of work are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?
  • (A) 3 : 2
  • (B) 2 : 3
  • (C) 3 : 4
  • (D) 4 : 3
βœ… Correct Answer: (D) 4 : 3