Q. A can do a piece of work in 20 days. He works it for 4 days and then B finish the work in 12 days. How long will it takes if both A and B works together?

  • (A) 8.5 days
  • (B) 6 days
  • (C) 10.3 days
  • (D) 12 days
βœ… Correct Answer: (A) 8.5 days