Q. Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work than when work together. If B worked alone, would take 4 and 1/2 hours more than when work together. The time required to finish the work together is ?
  • (A) 5 hours
  • (B) 4 hours
  • (C) 8 hours
  • (D) 6 hours
βœ… Correct Answer: (D) 6 hours