Q. A company employed 200 workers to complete a certain work in 150 days. If only one fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was ?

  • (A) 100
  • (B) 300
  • (C) 600
  • (D) 200
βœ… Correct Answer: (A) 100