Q. To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it ?
  • (A) 30 days
  • (B) 35 days
  • (C) 40 days
  • (D) 45 days
βœ… Correct Answer: (A) 30 days