Q. A does half as much work as B in three fourth of the time. If together they take 18 days to complete the work, how much time will B alone take to do it ?
  • (A) 40 days
  • (B) 45 days
  • (C) 50 days
  • (D) 30 days
βœ… Correct Answer: (D) 30 days