Q. A completes a work in 50 days. His efficiency increases by 25%. The new time required is:
β
Correct Answer: (C)
40 days
Explanation: New time = 50 × 100/125 = 40 days.
Explanation by: Deepak Sahoo
New time = 50 × 100/125 = 40 days.