Q. A and B together can complete a work in 24 days. B alone does 1/3 rd part of this work in 12 days. How many days will A alone take to complete the remaining work ?

  • (A) 24 days
  • (B) 36 days
  • (C) 48 days
  • (D) 72 days
  • Correct Answer - Option(C)