R Rakesh Kumar • 28.44K Points Instructor II Math Bookmark Embed Report View In MB-Short Q. A and B together can complete a work in 24 days. B alone does 1/3 rd part of this work in 12 days. How many days will A alone take to complete the remaining work ? (A) 24 days (B) 36 days (C) 48 days (D) 72 days Correct Answer - Option(C) Views: 63 Filed under category Math Share