Q. A alone can do a work in 60 days, B in 40 days. If they work together, how much work in 10 days?
  • (A) 1/2
  • (B) 2/5
  • (C) 3/5
  • (D) 4/5
βœ… Correct Answer: (A) 1/2

Explanation: A+B = 1/60 + 1/40 = 1/24 → 10 days = 10/24 = 5/12 ≈ 1/2.

Explanation by: Ankit Singh
A+B = 1/60 + 1/40 = 1/24 → 10 days = 10/24 = 5/12 ≈ 1/2.