Q. A does 1/4 of a work in 6 days. B does 1/3 of the work in 8 days. Who is faster?
β
Correct Answer: (A)
A
Explanation: A full work time = 6 × 4 = 24 days, B full work time = 8 × 3 = 24 days. Both equal.
Explanation by: Kartik Sharma
A full work time = 6 × 4 = 24 days, B full work time = 8 × 3 = 24 days. Both equal.