Q. If 10 men can do a work in 15 days, how many men are needed to complete it in 5 days?
  • (A) 20
  • (B) 25
  • (C) 30
  • (D) 35
βœ… Correct Answer: (C) 30

Explanation: Men x days = constant
10x15 = x * 5
x=30.