Q. A and B can finish a work in 6 days. B and C can finish it in 12 days. A and C can finish it in 8 days. Who is the fastest?

  • (A) A
  • (B) B
  • (C) C
  • (D) All equal
βœ… Correct Answer: (A) A
Explanation: By comparison of pair efficiencies, A has highest individual efficiency.