Q. A can complete a work in 28 days and B in 42 days. In how many days will they complete the work together?

  • (A) 16.8 days
  • (B) 18 days
  • (C) 20 days
  • (D) 21 days
βœ… Correct Answer: (A) 16.8 days
Explanation: Combined rate = 1/28 + 1/42 = 5/84. Time = 84/5 = 16.8 days.
Explanation by: Deepak Sahoo
Combined rate = 1/28 + 1/42 = 5/84. Time = 84/5 = 16.8 days.