Q. A can complete 4/7 of a work in 12 days. The whole work can be completed in:
β
Correct Answer: (C)
21 days
Explanation: Whole work = 12 × 7/4 = 21 days.
Explanation by: Deepak Sahoo
Whole work = 12 × 7/4 = 21 days.