Q. 45 men can complete a work in 16 days. 4 days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?

  • (A) 6
  • (B) 8
  • (C) 20/3
  • (D) 31/4
βœ… Correct Answer: (C) 20/3