πŸ“Š Construction Management
Q. A golden rule for the procurement of construction stones, suggests
  • (A) 100% at the site
  • (B) 67% at the site and 33% under procurement
  • (C) 50% at the site and 50% under procurement
  • (D) 33% at the site and 67% under procurement
πŸ’¬ Discuss
βœ… Correct Answer: (B) 67% at the site and 33% under procurement
πŸ“Š Construction Management
Q. The time with which direct cost does not reduce with the increase in time is known as
  • (A) Crash time
  • (B) Normal time
  • (C) Optimistic time
  • (D) Standard time
πŸ’¬ Discuss
βœ… Correct Answer: (B) Normal time
πŸ“Š Construction Management
Q. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
  • (A) The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest starttime
  • (B) The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
  • (C) Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. Interfering float is the difference between
  • (A) Total float and free float
  • (B) Total float and independentfloat
  • (C) Free float and independentfloat
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) Total float and free float
πŸ“Š Construction Management
Q. While filling the tender for any work, the contractor considers
  • (A) Site survey
  • (B) Availability of construction materials
  • (C) Availability of labour
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
  • (A) Rs. 8,43,750
  • (B) Rs. 8,75,000
  • (C) Rs. 10,50,000
  • (D) Rs. 11,56,250
πŸ’¬ Discuss
βœ… Correct Answer: (A) Rs. 8,43,750
πŸ“Š Construction Management
Q. A wheeled tractor hauling unit is working on firm earth. The total loaded weight distribution of this unit is: Drive wheels: 25000 kg Scraper wheels: 10000 kg If the coefficient of traction for wheeled tractor on firm earth is 0.5, the rimpull which this tractor can exert without slipping is
  • (A) 10000 kg
  • (B) 12500 kg
  • (C) 22500 kg
  • (D) 5000 kg
πŸ’¬ Discuss
βœ… Correct Answer: (B) 12500 kg
πŸ“Š Construction Management
Q. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
  • (A) 2.3% and 84.1%
  • (B) 97.7% and 84.1%
  • (C) 97.7 % and 15.9%
  • (D) 15.9% and 97.7%
πŸ’¬ Discuss
βœ… Correct Answer: (A) 2.3% and 84.1%
πŸ“Š Construction Management
Q. Power stations are generally treated as
  • (A) Light construction
  • (B) Heavy construction
  • (C) Industrial construction
  • (D) Electrical construction
πŸ’¬ Discuss
βœ… Correct Answer: (C) Industrial construction
πŸ“Š Construction Management
Q. For a given size of bucket, the ideal output of a dragline will be least in
  • (A) Moist loam
  • (B) Sand and gravel
  • (C) Good common earth
  • (D) Wet sticky clay
πŸ’¬ Discuss
βœ… Correct Answer: (D) Wet sticky clay