Q. The time corresponding to minimum total project cost is
  • (A) Crash time
  • (B) Normal time
  • (C) Optimistic time
  • (D) Between normal time and crash time
πŸ’¬ Discuss
βœ… Correct Answer: (D) Between normal time and crash time
πŸ“Š Construction Management
Q. Select the incorrect statement.
  • (A) Start float and finish float are always equal.
  • (B) Total float can be either start float or finish float.
  • (C) Start float and finish float need not be equal.
  • (D) Start float and finish float are the differences between activity times and notevent times.
πŸ’¬ Discuss
βœ… Correct Answer: (C) Start float and finish float need not be equal.
πŸ“Š Construction Management
Q. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
  • (A) Event
  • (B) Free float
  • (C) Dummy
  • (D) Constraint
πŸ’¬ Discuss
βœ… Correct Answer: (C) Dummy
πŸ“Š Construction Management
Q. PERT technique of network analysis is mainly useful for
  • (A) Small projects
  • (B) Large and complex projects
  • (C) Research and development projects
  • (D) Deterministic activities
πŸ’¬ Discuss
βœ… Correct Answer: (C) Research and development projects
πŸ“Š Construction Management
Q. The independent float affects only
  • (A) Preceding activities
  • (B) Succeeding activities
  • (C) The particular activity involved
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) The particular activity involved
πŸ“Š Construction Management
Q. Site order book is used for recording
  • (A) Instructions by the executive engineers
  • (B) Construction measurements
  • (C) Issue of store equipments
  • (D) Names of the casual labour
πŸ’¬ Discuss
βœ… Correct Answer: (A) Instructions by the executive engineers
πŸ“Š Construction Management
Q. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
  • (A) Duration
  • (B) Total float
  • (C) Free float
  • (D) Interfering float
πŸ’¬ Discuss
βœ… Correct Answer: (C) Free float
πŸ“Š Construction Management
Q. The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements
  • (A) (i), (ii) and (iv) are correct
  • (B) (ii), (iii) and (iv) are correct
  • (C) (i), (iii) and (iv) are correct
  • (D) (i), (ii) and (iii) are correct
πŸ’¬ Discuss
βœ… Correct Answer: (D) (i), (ii) and (iii) are correct