Construction Management MCQs | Page - 6
Dear candidates you will find MCQ questions of Construction Management here. Learn these questions and prepare yourself for coming examinations and interviews. You can check the right answer of any question by clicking on any option or by clicking view answer button.
Q. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
β
Correct Answer: (B)
25
Q. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
β
Correct Answer: (A)
Rs. 31050
Q. Output of a bulldozeris (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of thetractor Of these statement
β
Correct Answer: (B)
(i) and (iv) are correct
Q. For the execution of a project, a contractor is
β
Correct Answer: (D)
All the above
Q. The constraints in case of resource smoothening operation would be
β
Correct Answer: (B)
Project duration time
Q. The time which results in the leasi, possible construction cost of an activity, is known as
β
Correct Answer: (B)
Slow time
Q. The direct cost of a project with respect to normal time is
β
Correct Answer: (A)
minimum
Q. The object of technical planning, is
β
Correct Answer: (D)
All the above
Q. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
β
Correct Answer: (C)
3.5 and 25/36
Jump to