Q. PERT is
  • (A) An analytic in concept
  • (B) Limited of event oriented diagrams
  • (C) Used for research and development projects
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
  • (A) 20
  • (B) 25
  • (C) 35
  • (D) 15
πŸ’¬ Discuss
βœ… Correct Answer: (B) 25
πŸ“Š Construction Management
Q. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
  • (A) Rs. 31050
  • (B) Rs. 34500
  • (C) Rs. 37950
  • (D) Rs. 50000
πŸ’¬ Discuss
βœ… Correct Answer: (A) Rs. 31050
πŸ“Š Construction Management
Q. Output of a bulldozeris (i) Increased if drawbar HP of the tractor is increased for a given hauling distance (ii) Decreased if drawbar HP of the tractor is increased for a given hauling distance (iii) Increased if the hauling distance is increased for a given drawbar HP of the tractor (iv) Decreased if the hauling distance is increased for a given drawbar HP of thetractor Of these statement
  • (A) (i) and (iii) are correct
  • (B) (i) and (iv) are correct
  • (C) (ii) and (iii) are correct
  • (D) (ii) and (iv) are correct
πŸ’¬ Discuss
βœ… Correct Answer: (B) (i) and (iv) are correct
πŸ“Š Construction Management
Q. The constraints in case of resource smoothening operation would be
  • (A) Resources
  • (B) Project duration time
  • (C) Both resources and project duration time
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (B) Project duration time
πŸ“Š Construction Management
Q. The time which results in the leasi, possible construction cost of an activity, is known as
  • (A) Normal time
  • (B) Slow time
  • (C) Crash time
  • (D) Standard time
πŸ’¬ Discuss
βœ… Correct Answer: (B) Slow time
πŸ“Š Construction Management
Q. The object of technical planning, is
  • (A) Preparation of specifications
  • (B) Preparation of estimates
  • (C) Initiating the procurement action of resources
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
  • (A) 3.5 and 5/6
  • (B) 5 and 25/36
  • (C) 3.5 and 25/36
  • (D) 4 and 5/6
πŸ’¬ Discuss
βœ… Correct Answer: (C) 3.5 and 25/36