Q. Time and progress chart of a construction, is also known as
  • (A) Bar chart
  • (B) Gantt chart
  • (C) Modified Mile stone chart
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. Economic saving of time results by crashing
  • (A) Cheapest critical activity
  • (B) Cheapest noncritical activity
  • (C) Costliest critical activity
  • (D) Costliest noncritical activity
πŸ’¬ Discuss
βœ… Correct Answer: (A) Cheapest critical activity
πŸ“Š Construction Management
Q. In the given figure, the network of a project represents
  • (A) Activity of an excavation of a footing
  • (B) Activity of an excavation which starts at event No. 1 and ends at even No.2
  • (C) Activity of excavation which takes 8 units of time
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (C) Activity of excavation which takes 8 units of time
πŸ“Š Construction Management
Q. The technique for establishing and maintaining priorities among the various jobs of a project, is known
  • (A) Event flow scheduling technique
  • (B) Critical ratio scheduling
  • (C) Slotting technique forscheduling
  • (D) Short interval scheduling
πŸ’¬ Discuss
βœ… Correct Answer: (B) Critical ratio scheduling
πŸ“Š Construction Management
Q. Which of the following is a weakness of bar chart?
  • (A) Interdependencies of activities
  • (B) Project progress
  • (C) Uncertainties
  • (D) All of the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All of the above
πŸ“Š Construction Management
Q. Which one of the following represents an activity?
  • (A) Excavation for foundation
  • (B) Curing of concrete
  • (C) Setting of question paper
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. Which of the following excavators is most suitable for digging under water?
  • (A) Drag line
  • (B) Hoe
  • (C) Clam shell
  • (D) Dipper shovel
πŸ’¬ Discuss
βœ… Correct Answer: (A) Drag line
πŸ“Š Construction Management
Q. A CPM family includes
  • (A) CPA (Critical Path Analysis)
  • (B) CPP (Critical Path Plotted)
  • (C) MCE (Minimum Cost Expenditure)
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
  • (A) 1
  • (B) 2
  • (C) 3
  • (D) 4
πŸ’¬ Discuss
βœ… Correct Answer: (A) 1