Q. Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
  • (A) Ice
  • (B) Concrete
  • (C) Loose sand
  • (D) Earth
πŸ’¬ Discuss
βœ… Correct Answer: (D) Earth
πŸ“Š Construction Management
Q. Residential buildings are treated as
  • (A) Light construction
  • (B) Heavy construction
  • (C) Industrial construction
  • (D) Private construction
πŸ’¬ Discuss
βœ… Correct Answer: (A) Light construction
πŸ“Š Construction Management
Q. Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. Of these statements
  • (A) 1, 2 and 3 are correct
  • (B) 1 and 4 are correct
  • (C) 2, 3 and 4 are correct
  • (D) 1, 2 and 4 are correct
πŸ’¬ Discuss
βœ… Correct Answer: (B) 1 and 4 are correct
πŸ“Š Construction Management
Q. The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
  • (A) 19
  • (B) 14
  • (C) 24
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) 19
πŸ“Š Construction Management
Q. Consider the following activities in a building construction: 1. Concreting of roofslabs 2. Brick-jelly lime concrete terracing 3. Erection of form work forslab 4. Construction of parapet wall in terrace
  • (A) 1, 3, 2, 4
  • (B) 3, 1, 4, 2
  • (C) 3, 1, 2, 4
  • (D) 1, 3, 4, 2
πŸ’¬ Discuss
βœ… Correct Answer: (C) 3, 1, 2, 4
πŸ“Š Construction Management
Q. Military organisation is known as
  • (A) Line organisation
  • (B) Line and staff organisation
  • (C) Functional organisation
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) Line organisation
πŸ“Š Construction Management
Q. Mobilization advance up to 10% of the cost of work is given to a contractor
  • (A) On commencement of work at site for payment of loan taken by him
  • (B) For the purchase of construction materials
  • (C) For the payment of advances to labour and otherstaff
  • (D) For all activities required to start the work at site on finalization of the contract document
πŸ’¬ Discuss
βœ… Correct Answer: (D) For all activities required to start the work at site on finalization of the contract document
πŸ“Š Construction Management
Q. Pick up the PERT event from the following:
  • (A) Digging of foundation started
  • (B) Digging of foundation completed
  • (C) Laying of concrete started
  • (D) All the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) All the above
πŸ“Š Construction Management
Q. A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
  • (A) Rs. 4,75,000
  • (B) Rs. 5,75,000
  • (C) Rs. 6,50,000
  • (D) Rs. 8,50,000
πŸ’¬ Discuss
βœ… Correct Answer: (B) Rs. 5,75,000
πŸ“Š Construction Management
Q. The process of incorporating changes and rescheduling or replanning is called
  • (A) Resource levelling
  • (B) Resource smoothening
  • (C) Updating
  • (D) Critical path scheduling
πŸ’¬ Discuss
βœ… Correct Answer: (C) Updating