πŸ“Š Construction Project Management
Q. Road is the example of
  • (A) Building constructions.
  • (B) Infrastructure construction.
  • (C) Industrial construction.
  • (D) Special purpose projects
πŸ’¬ Discuss
βœ… Correct Answer: (B) Infrastructure construction.
πŸ“Š Construction Project Management
Q. What is the simplest and oldest type of organization?
  • (A) Matrix organization
  • (B) Line or military organization
  • (C) Line and staff organization
  • (D) Functional organization
πŸ’¬ Discuss
βœ… Correct Answer: (B) Line or military organization
πŸ“Š Construction Project Management
Q. What is Span of management?
  • (A) It is the number of persons to be supervised by a manager
  • (B) It is the number of years for management to remain active
  • (C) It is the average age of manager in a business
  • (D) It is the number of achievements of management
πŸ’¬ Discuss
βœ… Correct Answer: (A) It is the number of persons to be supervised by a manager
πŸ“Š Construction Project Management
Q. What is organization?
  • (A) Arrangement of persons in business
  • (B) Arrangement of machines on site
  • (C) Arrangement of money for business
  • (D) Arrangement of materials at site
πŸ’¬ Discuss
βœ… Correct Answer: (A) Arrangement of persons in business
πŸ“Š Construction Project Management
Q. What is 4M of construction?
  • (A) 4 types of organizations
  • (B) 4 resources for construction
  • (C) 4 types of construction managers
  • (D) 4 types of construction managers
πŸ’¬ Discuss
βœ… Correct Answer: (B) 4 resources for construction
πŸ“Š Construction Project Management
Q. In which type of tender advantage of keen bidding competition can be availed.
  • (A) Open tender or public tender
  • (B) Selected tender
  • (C) Negotiated tender
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) Open tender or public tender
πŸ“Š Construction Project Management
Q. What SMB stands for?
  • (A) Short measurement book
  • (B) Salient measurement book
  • (C) Standard measurement book
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) Standard measurement book
πŸ“Š Construction Project Management
Q. Which of the following contract is most suitable for road and bridges?
  • (A) BOT contract
  • (B) Cost plus fixed fee contract
  • (C) All in one contract
  • (D) Labour contract
πŸ’¬ Discuss
βœ… Correct Answer: (A) BOT contract

Jump to