πŸ“Š Construction Project Management
Q. In which of the following contract; contractor tries to complete job quickly?
  • (A) Item rate contract
  • (B) Cost plus fixed fee contract
  • (C) All in one contract
  • (D) Labour contract
πŸ’¬ Discuss
βœ… Correct Answer: (B) Cost plus fixed fee contract
πŸ“Š Construction Project Management
Q. In which of the following contract; contractor is quickly be agreed and work on job?
  • (A) Cost plus percentage rate contract
  • (B) Lump sum contract
  • (C) Piece work agreement
  • (D) Labour contract
πŸ’¬ Discuss
βœ… Correct Answer: (A) Cost plus percentage rate contract
πŸ“Š Construction Project Management
Q. In which of the following contract; contractor is not required to deposit SD?
  • (A) Item rate contract
  • (B) Lump sum contract
  • (C) Piece work agreement
  • (D) Labour contract
πŸ’¬ Discuss
βœ… Correct Answer: (C) Piece work agreement
πŸ“Š Construction Project Management
Q. In which of the following contract; contractor is required to offer a fixed sum for job in all respect as per given drawings and details?
  • (A) Item rate contract
  • (B) Lump-sum contract
  • (C) All in one contract
  • (D) Labor contract
πŸ’¬ Discuss
βœ… Correct Answer: (B) Lump-sum contract
πŸ“Š Construction Project Management
Q. For repair works at high level of multistoreyed buildings needle scaffolding is preferred
  • (A) As it is more stable
  • (B) As it looks better
  • (C) As it will not obstruct traffic at ground level.
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) As it will not obstruct traffic at ground level.
πŸ“Š Construction Project Management
Q. PPE stands for
  • (A) Personal protective equipment
  • (B) Preferred protective equipment
  • (C) Prohibited protective equipment
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) Personal protective equipment