πŸ“Š Software Quality Management (SQM)
Q. Which of the following is not one of the major categories of costs associated with quality?
  • (A) Prevention costs
  • (B) Appraisal costs
  • (C) Internal failures
  • (D) None of the above, they are all major categories of costs associated with quality
πŸ’¬ Discuss
βœ… Correct Answer: (D) None of the above, they are all major categories of costs associated with quality