Q. If a sample of parts is measured and the mean of the measurements is outside the control limits the process is
  • (A) In control, but not capable of producing within the established control limits
  • (B) Out of control and the process should be investigated for assignable variation
  • (C) Within the established control limits with only natural causes of variation
  • (D) Monitored closely to see if the next sample mean will also fall outside the control limits
πŸ’¬ Discuss
βœ… Correct Answer: (B) Out of control and the process should be investigated for assignable variation