πŸ“Š Software Quality Management (SQM)
Q. A review summary report answers which three questions?
  • (A) Terminate project, replace producer, and request a time extension
  • (B) What defects were found, what caused defects, who was responsible
  • (C) What was reviewed, who reviewed it, what were the findings
  • (D) None of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) What was reviewed, who reviewed it, what were the findings