Q. Sequencing (or dispatching)
  • (A) Assign dates to specific jobs or operations
  • (B) Assign jobs to work centers
  • (C) Specifies the order in which job should be done at each centre
  • (D) Assigns workers to jobs
πŸ’¬ Discuss
βœ… Correct Answer: (C) Specifies the order in which job should be done at each centre