πŸ“Š Entrepreneurship and Project Management
Q. .The asset created during the construction phase are utilised during the _____________
  • (A) The pre-investment phase
  • (B) The post-investment phase
  • (C) The reconstruction phase
  • (D) The normalisation phase
πŸ’¬ Discuss
βœ… Correct Answer: (D) The normalisation phase
πŸ“Š Entrepreneurship and Project Management
Q. ____________ phase in the project life cycle begin after the investment decision is taken.
  • (A) The post-investment phase
  • (B) The construction phase
  • (C) The normalisation phase
  • (D) The reconstruction phase
πŸ’¬ Discuss
βœ… Correct Answer: (B) The construction phase
πŸ“Š Entrepreneurship and Project Management
Q. _________________ is the first phase in project life cycle.
  • (A) The introduction phase
  • (B) The pre-investment phase
  • (C) The construction phase
  • (D) The normalisation phase
πŸ’¬ Discuss
βœ… Correct Answer: (B) The pre-investment phase
πŸ“Š Entrepreneurship and Project Management
Q. What are the the 3 basic dimensions of a project?
  • (A) Input, output and process
  • (B) Input, output and materials
  • (C) Input, output and social cost and benefits
  • (D) Input, output and features
πŸ’¬ Discuss
βœ… Correct Answer: (C) Input, output and social cost and benefits
πŸ“Š Entrepreneurship and Project Management
Q. _______________ is concerned with the collection, compilation and analysis of economic data for the eventual purpose of locating possible opportunities for investment.
  • (A) Project selection
  • (B) Project evaluation
  • (C) Project identification
  • (D) Project segmentation
πŸ’¬ Discuss
βœ… Correct Answer: (C) Project identification
πŸ“Š Entrepreneurship and Project Management
Q. A person who managed large project was termed as the entrepreneur in the _________.
  • (A) Earliest period.
  • (B) Middle ages.
  • (C) 17th century.
  • (D) 19th and 20th century.
πŸ’¬ Discuss
βœ… Correct Answer: (B) Middle ages.