πŸ“Š Operations Management
Q. Which of the following is a part of cost of quality?
  • (A) prevention cost
  • (B) appraisal cost
  • (C) failure cost
  • (D) all of these
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of these
πŸ“Š Operations Management
Q. In this sampling plan, the inspection results of two sample sizes are used to decide whether to accept or reject the complete lot.
  • (A) single sampling plan
  • (B) double sampling plan
  • (C) questionnaire
  • (D) census investigation
πŸ’¬ Discuss
βœ… Correct Answer: (B) double sampling plan
πŸ“Š Operations Management
Q. ……………………..starts from some data in the future and schedules the required operations in reverse sequence
  • (A) scheduling
  • (B) backward scheduling
  • (C) forward scheduling
  • (D) all of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) backward scheduling
πŸ“Š Operations Management
Q. ……………….is a time table for performing activities utilizing resources or allocating activities
  • (A) scheduling
  • (B) engineering
  • (C) reporting
  • (D) communication
πŸ’¬ Discuss
βœ… Correct Answer: (A) scheduling
πŸ“Š Operations Management
Q. Which of the following is an objective of scheduling?
  • (A) meet due dates
  • (B) minimise lead time
  • (C) minimise setup time and set up cost
  • (D) all of these
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of these
πŸ“Š Operations Management
Q. Which of the following factors affect capacity planning?
  • (A) type of product
  • (B) type of process
  • (C) skill level of workers
  • (D) all of these
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of these
πŸ“Š Operations Management
Q. …………………is the process of determining which job to start first and in what order other jobs should be processed on the machine or in work centre
  • (A) job sequencing
  • (B) priority rules
  • (C) batch production
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) job sequencing
πŸ“Š Operations Management
Q. Which of the following technique is employed for measuring work
  • (A) time study
  • (B) work sampling
  • (C) predetermined motion time studies
  • (D) all of these
πŸ’¬ Discuss
βœ… Correct Answer: (D) all of these
πŸ“Š Operations Management
Q. ………………….refers to the process of creating new products or modifying the existing ones within a predetermined time frame and cost price
  • (A) product design
  • (B) product development
  • (C) market development
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) product development
πŸ“Š Operations Management
Q. ……………refers to the development of the concept or idea of a product in terms of specifications which are required for transforming the idea in to product
  • (A) product design
  • (B) product development
  • (C) (a) and (b)
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) product design