Q. A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • (A) 8 days
  • (B) 12 days
  • (C) 16 days
  • (D) 6 days
βœ… Correct Answer: (D) 6 days