πŸ“Š Process Planning and Cost Estimation
Q. Land use, transportation and road network plans are
  • (A) inter linked
  • (B) intra linked
  • (C) not linked
  • (D) depends on the network
πŸ’¬ Discuss
βœ… Correct Answer: (A) inter linked

Explanation: land use, transportation and road network plans are inter linked to each other and they are inseparable.

πŸ“Š Process Planning and Cost Estimation
Q. The first stage in the function of traffic engineering department is?
  • (A) planning and design
  • (B) collection of data
  • (C) investigations
  • (D) finance
πŸ’¬ Discuss
βœ… Correct Answer: (B) collection of data

Explanation: the first stage in the function of the traffic engineering department is a collection of data followed by analysis and design.

πŸ“Š Process Planning and Cost Estimation
Q. Traffic forecast is not influenced by
  • (A) gdp
  • (B) industrial output
  • (C) population
  • (D) weather
πŸ’¬ Discuss
βœ… Correct Answer: (D) weather

Explanation: weather cannot influence the traffic forecast, as it is not related to traffic engineering, the remaining directly or indirectly are related to the traffic.

πŸ“Š Process Planning and Cost Estimation
Q. The NHDP are being undertaken by private companies on the basis of
  • (A) profit
  • (B) revenue
  • (C) bot
  • (D) commission basis
πŸ’¬ Discuss
βœ… Correct Answer: (C) bot

Explanation: in india mostly private and govt. sectors follow bot which means build operate transfer, it is built by a private firm and later transferred to govt.

πŸ“Š Process Planning and Cost Estimation
Q. The traffic will increase if the
  • (A) price of fuel decreases
  • (B) price of vehicles decreases
  • (C) price of fuel decreases
  • (D) price of vehicles decreases
πŸ’¬ Discuss
βœ… Correct Answer: (B) price of vehicles decreases

Explanation: the traffic increases if the prices of vehicle decreases, price of fuel may increase and decrease, but if the price of the vehicle decreases then the traffic increases.

πŸ“Š Process Planning and Cost Estimation
Q. The process of working out the cost per unit of each item is known as
  • (A) work
  • (B) sheet
  • (C) data
  • (D) analysis
πŸ’¬ Discuss
βœ… Correct Answer: (C) data

Explanation: the preparation of a detailed estimate comprises of working out quantities of different items of work and then determining the cost of each item. the

πŸ“Š Process Planning and Cost Estimation
Q. While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per
  • (A) special data book
  • (B) standard data book
  • (C) special data record
  • (D) specific data record
πŸ’¬ Discuss
βœ… Correct Answer: (B) standard data book

Explanation: while fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per the standard data book. however, the rates of labour and materials are obtained from the current standard scheduled of rates.

πŸ“Š Process Planning and Cost Estimation
Q. In the case of works which require some special types of equipment, an amount of
  • (A) 1-2
  • (B) 5-9
  • (C) 12-18
  • (D) 16-20
πŸ’¬ Discuss
βœ… Correct Answer: (A) 1-2

Explanation: in the case of works that require some special types of equipment, an amount of 1-2 percent of the estimated cost is given. while preparing a detailed estimate, it is also important to select a suitable site of work to reduce damage during the loading and unloading of materials.

πŸ“Š Process Planning and Cost Estimation
Q. Which of the following is not a method used for preparing approximate estimates?
  • (A) cubical contents method
  • (B) unit base method
  • (C) plinth area method
  • (D) cylindrical base method
πŸ’¬ Discuss
βœ… Correct Answer: (D) cylindrical base method

Explanation: there are various methods used for preparing approximate estimates. these are the plinth area method, unit base method

πŸ“Š Process Planning and Cost Estimation
Q. In the plinth area method, the cost of construction is computed by the multiplication of
  • (A) plinth length and rate
  • (B) plinth breadth and rate
  • (C) plinth area and plinth area rate
  • (D) plinth volume and plinth length rate
πŸ’¬ Discuss
βœ… Correct Answer: (C) plinth area and plinth area rate

Explanation: in the plinth area method, the cost of construction is computed by the multiplication of plinth area and plinth area rate. this area is calculated by multiplying the length and the breadth.

Jump to