M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. …………….. is the provision to increase the contract price increase in the Cost of construction over a particular level (A) Escalation clause (B) Desecration clause (C) Retention money (D) work certified ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Escalation clause
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. The work in the process of completion is known as ……………. (A) Work certified (B) work in progress (C) Work un certified (D) notional profit ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) work in progress
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. ……….. is the portion of work certified not paid by the contractee till completion of the work (A) Work certified (B) Uncertified (C) Retention money (D) notional profit ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) Retention money
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. The person who gives the work on contract is known as …… (A) Contractor (B) contractee (C) Sub contraction (D) sub contractee ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) contractee
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. A contract in which the contractor is given the lost of work done plus a certain percentage for profit is called ……………………. (A) Cost plus contract (B) Sub contract (C) Fixed price contract (D) none of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Cost plus contract
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. Provision for increase in the contract price to accommodate increase in material and labour cost (A) De escalation clause (B) fluctuating price (C) Fixed price (D) Escalation price ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) Escalation price
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. A cost do not change with changes in the level of activity is …………. (A) Variable cost (B) fixed cost (C) sunk cost (D) total cost ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) fixed cost
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. Cost of producing an additional unit of output is …………… (A) Historical cost (B) marginal cost (C) fixed cost (D) total cost ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) marginal cost
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. ……… is the difference b/w the sales and marginal cost of sale (A) Profit (B) contribution (C) p/v ratio (D) none f these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) contribution
M Mr. Dubey π Coach β 103.11K Points π Applied Cost Accounting Q. Where actual loss in a process is less than the anticipated loss , the difference b/w the two is considered to be ………….. (A) Normal los (B) Abnormal gain (C) normal gain (D) None of ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Abnormal gain