πŸ“Š Applied Cost Accounting
Q. Contract testing is a basic method of
  • (A) Specific costing
  • (B) Specific order costing
  • (C) Economic batch costing
  • (D) Economic order costing
πŸ’¬ Discuss
βœ… Correct Answer: (B) Specific order costing
πŸ“Š Applied Cost Accounting
Q. When the completion stage of a contract is less than ¼ of the total expenditure on the contract is transferred to
  • (A) Profit & Loss account
  • (B) Work certified account
  • (C) Work in progress account
  • (D) Contract account
πŸ’¬ Discuss
βœ… Correct Answer: (C) Work in progress account
πŸ“Š Applied Cost Accounting
Q. In contract costing most of the items of cost are
  • (A) Direct
  • (B) Indirect
  • (C) Variable
  • (D) Semivariable
πŸ’¬ Discuss
βœ… Correct Answer: (A) Direct
πŸ“Š Applied Cost Accounting
Q. Job costing can be done in conjunction with
  • (A) Standard costing
  • (B) Process costing
  • (C) Multiple costing
  • (D) Marginal costing
πŸ’¬ Discuss
βœ… Correct Answer: (D) Marginal costing
πŸ“Š Applied Cost Accounting
Q. If the contract is almost complete, the amount of profit generally transferred to profit and loss account is equal to
  • (A) Estimated profit*(Contract price/Work certified)
  • (B) National profit*(Cash Received/Work certified)
  • (C) Estimated profit*(Work certified/Contract price)
  • (D) Work certified*(Contract price/Estimated price)
πŸ’¬ Discuss
βœ… Correct Answer: (C) Estimated profit*(Work certified/Contract price)
πŸ“Š Applied Cost Accounting
Q. In contract costing credit is taken only for a part of the profit on
  • (A) Incomplete contract
  • (B) Complete contract
  • (C) Estimated contract
  • (D) Initial contract
πŸ’¬ Discuss
βœ… Correct Answer: (A) Incomplete contract
πŸ“Š Applied Cost Accounting
Q. In job costing each job is a ……………..to which all cost are assigned
  • (A) Profit unit
  • (B) Cost unit
  • (C) Expenses
  • (D) Variable
πŸ’¬ Discuss
βœ… Correct Answer: (B) Cost unit
πŸ“Š Applied Cost Accounting
Q. In contract costing payment of cash to the contractor is made on the basis of
  • (A) Estimated work
  • (B) Standard work
  • (C) Certified work
  • (D) Uncertified work
πŸ’¬ Discuss
βœ… Correct Answer: (C) Certified work
πŸ“Š Applied Cost Accounting
Q. ……………..budget gives different budgeted cost for different levels of activity
  • (A) Flexible budget
  • (B) Fixed budget
  • (C) Master budget
  • (D) Production budget
πŸ’¬ Discuss
βœ… Correct Answer: (A) Flexible budget
πŸ“Š Applied Cost Accounting
Q. ……………..budget provides information about the materials to be acquired from the market
  • (A) Material budget
  • (B) Production budget
  • (C) Cash budget
  • (D) Purchase budget
πŸ’¬ Discuss
βœ… Correct Answer: (D) Purchase budget