Q. ……………………… study is a systematic method adopted to find out the possibility and practicability of starting a project.
  • (A) profitability
  • (B) liquidity
  • (C) feasibility
  • (D) viability
πŸ’¬ Discuss
βœ… Correct Answer: (C) feasibility
πŸ“Š Entrepreneurship Development
Q. ………………………… is the difference between the actual sales and break even sales.
  • (A) margin of safety
  • (B) fixed cost
  • (C) contribution
  • (D) profit
πŸ’¬ Discuss
βœ… Correct Answer: (A) margin of safety
πŸ“Š Entrepreneurship Development
Q. Activities that can be accomplished simultaneously are called……………activities.
  • (A) critical
  • (B) preceding
  • (C) succeeding
  • (D) concurrent
πŸ’¬ Discuss
βœ… Correct Answer: (D) concurrent
πŸ“Š Entrepreneurship Development
Q. Activities that cannot be started until one or more of other activities are completed but immediately follow are called…………………..
  • (A) critical
  • (B) preceding
  • (C) succeeding
  • (D) concurrent
πŸ’¬ Discuss
βœ… Correct Answer: (C) succeeding
πŸ“Š Entrepreneurship Development
Q. ……………are activities that must be completed immediately prior to the start of another activity.
  • (A) critical
  • (B) preceding
  • (C) succeeding
  • (D) concurrent
πŸ’¬ Discuss
βœ… Correct Answer: (B) preceding
πŸ“Š Entrepreneurship Development
Q. Activities lying on the critical path are known as……………………..activities.
  • (A) critical
  • (B) preceding
  • (C) succeeding
  • (D) concurrent
πŸ’¬ Discuss
βœ… Correct Answer: (A) critical
πŸ“Š Entrepreneurship Development
Q. Critical path is the longest ………………………….in the network
  • (A) slack
  • (B) activity
  • (C) event
  • (D) path
πŸ’¬ Discuss
βœ… Correct Answer: (D) path
πŸ“Š Entrepreneurship Development
Q. ……is the unbroken chain of activities from start event to end event in the network diagram.
  • (A) slack
  • (B) activity
  • (C) network
  • (D) path
πŸ’¬ Discuss
βœ… Correct Answer: (D) path