Q. Which of the following is not a technique of financial analysis:
  • (A) ratio analysis.
  • (B) risk analysis.
  • (C) cash flow analysis.
  • (D) fund flow analysis.
πŸ’¬ Discuss
βœ… Correct Answer: (B) risk analysis.
πŸ“Š Entrepreneurship Development
Q. ……….shows movement of cash into and out of the firm and its net effect on balance sheet.
  • (A) cash flow
  • (B) fund flow
  • (C) ratio
  • (D) breakeven
πŸ’¬ Discuss
βœ… Correct Answer: (A) cash flow
πŸ“Š Entrepreneurship Development
Q. …………shows the changes in assets, liabilities and net worth between two balance sheet dates.
  • (A) cash flow
  • (B) fund flow
  • (C) ratio
  • (D) breakeven
πŸ’¬ Discuss
βœ… Correct Answer: (B) fund flow
πŸ“Š Entrepreneurship Development
Q. Estimated time required in normal conditions complete an activity is ………………
  • (A) pessimistic time
  • (B) optimistic time
  • (C) most likely time
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (C) most likely time
πŸ“Š Entrepreneurship Development
Q. Maximum possible time to complete an activity is ………………………
  • (A) pessimistic time
  • (B) optimistic time
  • (C) most likely time
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) pessimistic time
πŸ“Š Entrepreneurship Development
Q. Shortest possible time to complete an activity is ………………………
  • (A) pessimistic time
  • (B) optimistic time
  • (C) most likely time
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) optimistic time
πŸ“Š Entrepreneurship Development
Q. Decision regarding factory design is part of :
  • (A) network analysis.
  • (B) financial analysis.
  • (C) technical analysis.
  • (D) social cost benefit analysis.
πŸ’¬ Discuss
βœ… Correct Answer: (C) technical analysis.
πŸ“Š Entrepreneurship Development
Q. Which of the following is a technique of project identification:
  • (A) desk research.
  • (B) sensitivity analysis.
  • (C) cvp analysis.
  • (D) none of these.
πŸ’¬ Discuss
βœ… Correct Answer: (A) desk research.
πŸ“Š Entrepreneurship Development
Q. Which of the following is not a phase in the project life cycle:
  • (A) pre- investment phase.
  • (B) construction phase.
  • (C) normalization phase.
  • (D) growth phase.
πŸ’¬ Discuss
βœ… Correct Answer: (D) growth phase.