Q. The maximise criteria is ...........................
  • (A) Optimistic
  • (B) Pessimistic
  • (C) Neutral
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) Pessimistic
πŸ“Š Management Science
Q. .......................... is the duration by which an activity can be delayed without delaying the project.
  • (A) Slack
  • (B) Total float
  • (C) Both a and b
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) Total float
πŸ“Š Management Science
Q. In a network diagram, activity is denoted by ............................
  • (A) Node
  • (B) Arrow
  • (C) Triangle
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) Arrow
πŸ“Š Management Science
Q. ......................... is a scheme or design of something intended to do.
  • (A) Network
  • (B) Float
  • (C) Project
  • (D) Program
πŸ’¬ Discuss
βœ… Correct Answer: (A) Network
πŸ“Š Management Science
Q. ............................ is the latest time by which an activity can be finished without delaying the completion of the project.
  • (A) LST
  • (B) LFT
  • (C) EFT
  • (D) EST
πŸ’¬ Discuss
βœ… Correct Answer: (B) LFT
πŸ“Š Management Science
Q. The EST + activity duration = ..............................
  • (A) Earliest Finish Time
  • (B) Latest Start Time
  • (C) Latest Finish Time
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) Earliest Finish Time
πŸ“Š Management Science
Q. ..................... is the duration by which an activity can be delayed without delaying the completion of the project.
  • (A) Earliest Start Time
  • (B) Earliest Finish Time
  • (C) Latest Start Time
  • (D) Latest Finish Time
πŸ’¬ Discuss
βœ… Correct Answer: (C) Latest Start Time
πŸ“Š Management Science
Q. ............................ is the sequence of activities which determines the total project duration.
  • (A) Critical path
  • (B) Network
  • (C) Non-critical activities
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) Critical path
πŸ“Š Management Science
Q. Activities that cannot be started until one or more of the other activities are completed, are called..........................................
  • (A) Dummy activities
  • (B) Initial activities
  • (C) Successor activities
  • (D) Predecessor activities
πŸ’¬ Discuss
βœ… Correct Answer: (C) Successor activities