G Gopal Sharma π Tutor III β 38.32K Points π Management Science Q. The maximise criteria is ........................... (A) Optimistic (B) Pessimistic (C) Neutral (D) None of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Pessimistic
V Vinay π Mover β 28.75K Points π Management Science Q. .......................... is the duration by which an activity can be delayed without delaying the project. (A) Slack (B) Total float (C) Both a and b (D) None of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Total float
P Praveen Singh π Tutor III β 36.81K Points π Management Science Q. In a network diagram, activity is denoted by ............................ (A) Node (B) Arrow (C) Triangle (D) None of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Arrow
A Admin π Coach β 38.23K Points π Management Science Q. ......................... is a scheme or design of something intended to do. (A) Network (B) Float (C) Project (D) Program ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Network
V Vinay π Mover β 28.75K Points π Management Science Q. ............................ is the latest time by which an activity can be finished without delaying the completion of the project. (A) LST (B) LFT (C) EFT (D) EST ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) LFT
V Vijay Sangwan π Mover β 28.62K Points π Management Science Q. The EST + activity duration = .............................. (A) Earliest Finish Time (B) Latest Start Time (C) Latest Finish Time (D) None of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Earliest Finish Time
P Priyanka Tomar π Tutor III β 35.28K Points π Management Science Q. ..................... is the duration by which an activity can be delayed without delaying the completion of the project. (A) Earliest Start Time (B) Earliest Finish Time (C) Latest Start Time (D) Latest Finish Time ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) Latest Start Time
V Vijay Sangwan π Mover β 28.62K Points π Management Science Q. PERT emphasises on ........................... (A) Activity (B) Time (C) Cost (D) None of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Time
R Rakesh Kumar π Hard Worker β 28.44K Points π Management Science Q. ............................ is the sequence of activities which determines the total project duration. (A) Critical path (B) Network (C) Non-critical activities (D) None of these ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Critical path
R Rakesh Kumar π Hard Worker β 28.44K Points π Management Science Q. Activities that cannot be started until one or more of the other activities are completed, are called.......................................... (A) Dummy activities (B) Initial activities (C) Successor activities (D) Predecessor activities ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) Successor activities