Q. Activities lying on critical path are called ............................
  • (A) Critical activities
  • (B) Non-critical activities
  • (C) Dummy activities
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) Critical activities
πŸ“Š Management Science
Q. An event which represents the beginning of more than one activity is a :
  • (A) Merge event
  • (B) Net event
  • (C) Burst event
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (C) Burst event
πŸ“Š Management Science
Q. ......................... is a series of activities related to a project.
  • (A) Network
  • (B) Transportation Model
  • (C) Assignment model
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) Network
πŸ“Š Management Science
Q. An activity which does not consume either resource or time is called .............................
  • (A) Predecessor activity
  • (B) Successor activity
  • (C) Dummy activity
  • (D) Terminal activity
πŸ’¬ Discuss
βœ… Correct Answer: (C) Dummy activity
πŸ“Š Management Science
Q. ................... is an event oriented network diagram.
  • (A) CPM
  • (B) PERT
  • (C) Histogram
  • (D) Ogive
πŸ’¬ Discuss
βœ… Correct Answer: (B) PERT
πŸ“Š Management Science
Q. ......................... is activity oriented network diagram.
  • (A) CPM
  • (B) PERT
  • (C) Histogram
  • (D) Ogive
πŸ’¬ Discuss
βœ… Correct Answer: (A) CPM
πŸ“Š Management Science
Q. In network diagram, events are commonly represented by .........................
  • (A) Arrows
  • (B) Nodes
  • (C) Triangles
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) Nodes
πŸ“Š Management Science
Q. An activity which must be completed before commencement of one or more other activities is called.................................
  • (A) Successor activity
  • (B) Predecessor activity
  • (C) Dummy activity
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) Predecessor activity
πŸ“Š Management Science
Q. PERT stand for:
  • (A) Performance Evaluation Review Technique
  • (B) Programme Evaluation Review Technique
  • (C) Programme Evaluation Research Technique
  • (D) None of these
πŸ’¬ Discuss
βœ… Correct Answer: (B) Programme Evaluation Review Technique
πŸ“Š Management Science
Q. Non-negativity constraints are written as ......................
  • (A) Equality
  • (B) Non-equality
  • (C) Greater than or equal to
  • (D) Less than or equal to
πŸ’¬ Discuss
βœ… Correct Answer: (C) Greater than or equal to