πŸ“Š Project Management
Q. The basic nature of a project is a/an _____ one.
  • (A) permanent
  • (B) temporary
  • (C) (A) or (B)
  • (D) Both (A) and (B)
πŸ’¬ Discuss
βœ… Correct Answer: (B) temporary
πŸ“Š Project Management
Q. Assembling project team and assigning their responsibilities are done during which phase of a project management?
  • (A) Initiation
  • (B) Planning
  • (C) Execution
  • (D) Closure
πŸ’¬ Discuss
βœ… Correct Answer: (A) Initiation
πŸ“Š Project Management
Q. A ____________ is a temporary endeavor undertaken to create a unique product service or result.
  • (A) Assignment
  • (B) Product
  • (C) Research
  • (D) Project
πŸ’¬ Discuss
βœ… Correct Answer: (D) Project
πŸ“Š Project Management
Q. What is associated with product risk?
  • (A) Control of test item
  • (B) Negative consequences
  • (C) non-availability of test environment
  • (D) Test object
πŸ’¬ Discuss
βœ… Correct Answer: (D) Test object
πŸ“Š Project Management
Q. Risk management is responsibility of the
  • (A) Customer
  • (B) Investor
  • (C) Developer
  • (D) Project team
πŸ’¬ Discuss
βœ… Correct Answer: (D) Project team
πŸ“Š Project Management
Q. Which of the following is not a tool or technique used during the Risk Quantification Process?
  • (A) Risk Categorization
  • (B) Contingency planning
  • (C) Probability and Impact Matrix
  • (D) Risk Data Quality Assessment
πŸ’¬ Discuss
βœ… Correct Answer: (B) Contingency planning
πŸ“Š Project Management
Q. Reserve analysis is NOT a Tool/Technique in which of the following processes?
  • (A) Cost Estimation
  • (B) Activity Duration estimation
  • (C) Cost Budgeting
  • (D) Activity Resource Estimation
πŸ’¬ Discuss
βœ… Correct Answer: (D) Activity Resource Estimation
πŸ“Š Project Management
Q. Risk Management Plan may include
  • (A) Budgeting, Timing, Thresholds, Methodology
  • (B) Risks, Triggers, Inputs to other processes
  • (C) Avoided, Transferred, Mitigated and Accepted Risks
  • (D) Risk Response Audits, Earned Value Analysis, Technical Performance Measurement
πŸ’¬ Discuss
βœ… Correct Answer: (A) Budgeting, Timing, Thresholds, Methodology
πŸ“Š Project Management
Q. You have just completed Qualitative Risk Analysis of the project. What should you be doing next?
  • (A) Plan Risk Management
  • (B) Perform Quantitative Risk Analysis
  • (C) Plan Risk Responses
  • (D) Control Risks
πŸ’¬ Discuss
βœ… Correct Answer: (B) Perform Quantitative Risk Analysis
πŸ“Š Project Management
Q. Supplier risk is highest with ___________.
  • (A) Cost plus incentives fee.
  • (B) Cost sharing.
  • (C) Firm fixed price contract.
  • (D) Fixed price plus incentives.
πŸ’¬ Discuss
βœ… Correct Answer: (C) Firm fixed price contract.