R Ram Sharma π Coach β 193.88K Points π Project Management Q. The basic nature of a project is a/an _____ one. (A) permanent (B) temporary (C) (A) or (B) (D) Both (A) and (B) ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) temporary
V Vikash Gupta π Tutor III β 33.56K Points π Project Management Q. Assembling project team and assigning their responsibilities are done during which phase of a project management? (A) Initiation (B) Planning (C) Execution (D) Closure ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Initiation
R Ranjeet π Tutor III β 34.60K Points π Project Management Q. A ____________ is a temporary endeavor undertaken to create a unique product service or result. (A) Assignment (B) Product (C) Research (D) Project ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) Project
V Vikash Gupta π Tutor III β 33.56K Points π Project Management Q. What is associated with product risk? (A) Control of test item (B) Negative consequences (C) non-availability of test environment (D) Test object ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) Test object
V Vijay Sangwan π Mover β 28.62K Points π Project Management Q. Risk management is responsibility of the (A) Customer (B) Investor (C) Developer (D) Project team ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) Project team
A Admin π Coach β 38.23K Points π Project Management Q. Which of the following is not a tool or technique used during the Risk Quantification Process? (A) Risk Categorization (B) Contingency planning (C) Probability and Impact Matrix (D) Risk Data Quality Assessment ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Contingency planning
P Priyanka Tomar π Tutor III β 35.28K Points π Project Management Q. Reserve analysis is NOT a Tool/Technique in which of the following processes? (A) Cost Estimation (B) Activity Duration estimation (C) Cost Budgeting (D) Activity Resource Estimation ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) Activity Resource Estimation
G Gopal Sharma π Tutor III β 38.32K Points π Project Management Q. Risk Management Plan may include (A) Budgeting, Timing, Thresholds, Methodology (B) Risks, Triggers, Inputs to other processes (C) Avoided, Transferred, Mitigated and Accepted Risks (D) Risk Response Audits, Earned Value Analysis, Technical Performance Measurement ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) Budgeting, Timing, Thresholds, Methodology
R Rakesh Kumar π Hard Worker β 28.44K Points π Project Management Q. You have just completed Qualitative Risk Analysis of the project. What should you be doing next? (A) Plan Risk Management (B) Perform Quantitative Risk Analysis (C) Plan Risk Responses (D) Control Risks ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) Perform Quantitative Risk Analysis
V Vinay π Mover β 28.75K Points π Project Management Q. Supplier risk is highest with ___________. (A) Cost plus incentives fee. (B) Cost sharing. (C) Firm fixed price contract. (D) Fixed price plus incentives. ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) Firm fixed price contract.