πŸ“Š Management Science
Q. It ………. at which an activity can start.
  • (A) est
  • (B) eft
  • (C) lst
  • (D) lft
πŸ’¬ Discuss
βœ… Correct Answer: (A) est
πŸ“Š Management Science
Q. Activities lying on the critical path are called………….
  • (A) net work
  • (B) critical path
  • (C) critical activities
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) critical activities
πŸ“Š Management Science
Q. ………..is that sequence of activities which determines the total project time.
  • (A) net work
  • (B) critical path
  • (C) critical activities
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (B) critical path
πŸ“Š Management Science
Q. While solving an LP problem, infeasibility may be removed by
  • (A) adding another constraint
  • (B) adding another variable
  • (C) removing a constraint
  • (D) removing a variable
πŸ’¬ Discuss
βœ… Correct Answer: (C) removing a constraint
πŸ“Š Management Science
Q. Alternative solutions exists of an LP model when
  • (A) one of the constraints is redundant.
  • (B) objective function equation is parallel to one of the constraints
  • (C) two constraints are parallel.
  • (D) all of the above
πŸ’¬ Discuss
βœ… Correct Answer: (B) objective function equation is parallel to one of the constraints
πŸ“Š Management Science
Q. Constraint in LP problem are called active if they
  • (A) represent optimal solution
  • (B) at optimality do not consume all the available resources
  • (C) both of (a) and (b)
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (A) represent optimal solution
πŸ“Š Management Science
Q. If two constraints do not intersect in the positive quadrant of the graph, then
  • (A) the problem is infeasible
  • (B) the solution is unbounded
  • (C) one of the constraints is redundant
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (D) none of the above
πŸ“Š Management Science
Q. An event which represents the beginning of more than one activity is known as ………..event.
  • (A) merge
  • (B) net
  • (C) burst
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (C) burst
πŸ“Š Management Science
Q. ………. is a series of related activities which result in some product or services.
  • (A) network
  • (B) transportation model
  • (C) assignment
  • (D) none of these
πŸ’¬ Discuss
βœ… Correct Answer: (A) network
πŸ“Š Management Science
Q. In linear programming problem if all constraints are less than or equal to, then the feasible region is
  • (A) above lines
  • (B) below the lines
  • (C) unbounded
  • (D) none of the above
πŸ’¬ Discuss
βœ… Correct Answer: (B) below the lines