Q. …….. is a scheme or design of something intended or device.
  • (A) programme
  • (B) project
  • (C) network
  • (D) float
πŸ’¬ Discuss
βœ… Correct Answer: (C) network
πŸ“Š Management Science
Q. Full form of PERT is
  • (A) performance evaluation review technique
  • (B) programme evaluation review technique
  • (C) programme evaluation research technique
  • (D) none of these.
πŸ’¬ Discuss
βœ… Correct Answer: (B) programme evaluation review technique
πŸ“Š Management Science
Q. ……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity
  • (A) slack
  • (B) total float
  • (C) free float
  • (D) independent float
πŸ’¬ Discuss
βœ… Correct Answer: (C) free float
πŸ“Š Management Science
Q. ……………is the duration by which an activity can be delayed without delaying the project
  • (A) slack
  • (B) total float
  • (C) free float
  • (D) independent float
πŸ’¬ Discuss
βœ… Correct Answer: (B) total float
πŸ“Š Management Science
Q. ……….is the latest time by which an activity can be finished without delaying the completion of the project.
  • (A) est
  • (B) eft
  • (C) lst
  • (D) lft
πŸ’¬ Discuss
βœ… Correct Answer: (D) lft
πŸ“Š Management Science
Q. ………. is the latest time by which an activity can be started without delaying the completion of the project.
  • (A) est
  • (B) eft
  • (C) lst
  • (D) lft
πŸ’¬ Discuss
βœ… Correct Answer: (C) lst