V Vijay Sangwan π Mover β 28.62K Points π Management Science Q. …….. is a scheme or design of something intended or device. (A) programme (B) project (C) network (D) float ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) network
P Priyanka Tomar π Tutor III β 35.28K Points π Management Science Q. Full form of PERT is (A) performance evaluation review technique (B) programme evaluation review technique (C) programme evaluation research technique (D) none of these. ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) programme evaluation review technique
P Praveen Singh π Tutor III β 36.81K Points π Management Science Q. PERT emphasis on ……….. (A) time (B) activity (C) a) and b) (D) none of the above ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) time
V Vijay Sangwan π Mover β 28.62K Points π Management Science Q. ………. is event oriented. (A) cpm (B) pert (C) lp (D) none of the above ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) pert
V Vijay Sangwan π Mover β 28.62K Points π Management Science Q. ……….is activity oriented. (A) cpm (B) pert (C) lp (D) none of the above ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (A) cpm
P Praveen Singh π Tutor III β 36.81K Points π Management Science Q. ……… is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity (A) slack (B) total float (C) free float (D) independent float ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) free float
P Priyanka Tomar π Tutor III β 35.28K Points π Management Science Q. ……………is the duration by which an activity can be delayed without delaying the project (A) slack (B) total float (C) free float (D) independent float ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) total float
S Shiva Ram π Master β 30.44K Points π Management Science Q. ……….is the latest time by which an activity can be finished without delaying the completion of the project. (A) est (B) eft (C) lst (D) lft ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (D) lft
P Priyanka Tomar π Tutor III β 35.28K Points π Management Science Q. ………. is the latest time by which an activity can be started without delaying the completion of the project. (A) est (B) eft (C) lst (D) lft ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (C) lst
V Vijay Sangwan π Mover β 28.62K Points π Management Science Q. ………… is the earliest starting time plus activity time. (A) est (B) eft (C) lst (D) lft ποΈ Show Answer π¬ Discuss π Share β‘Menu β Correct Answer: (B) eft